M18 Northbound (Only) Closure-Monday, March 10, 2014 between Junction 14 (Barefield) and Junction 15 (Crusheen)

On Monday, March 10th, 2014 the M18 Northbound Only (Galway) between Junction14 (Barefield) and Junction 15 (Crusheen) will be closed until Friday, March 14th

Closure will commence on Monday, March 10th 09:00hr (9:00AM) and will be reopened on Friday, March 14th at approximately 14:00hr (2:00PM) in advance of Bank Holiday Weekend.

  • Drainage assessment and improvement works will take place during this closure.
  • The M18 Southbound carriageway will remain open to traffic for the duration of the works.


Traffic Diversion Details

Traffic will be diverted from the existing M18 Northbound onto the R458 (N18-Old Road) at Junction 14 Barefield and then returning to M18 Northbound at Junction 15 onto the Motorway.